Skip to content
Back to skills

Sprint Plan

ASecurity

Plans a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, or balancing scope against velocity. Triggers on: sprint planning, sprint plan, capacity planning, sprint scope, story points, sprint goal, backlog grooming, sprint prep, what do we build this sprint.

  • 3 stars
  • 0 votes
  • 0 copies
  • 2 views
  • Added September 1, 2026
businessgoapiperformance

Works with

  • api

Security analysis

A100/100

Scanned September 1, 2026

npx -y skills add alunadev/ald-skills --skill sprint-plan --agent claude-code

Installs into .claude/skills of the current project.

Are you the author of Sprint Plan?

Add the live security badge to your README. It updates with every re-scan.

Security grade badge for Sprint Plan
[![Security: A — Skills Directory](https://www.skillsdirectory.com/api/skills/alunadev-sprint-plan/badge)](https://www.skillsdirectory.com/skills/alunadev-sprint-plan)

More formats (shields.io, HTML) on the badges page. Keep it an A: scan every change in CI with Pro.

Download with Pro
SKILL.md
---
name: sprint-plan
description: "Plans a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, or balancing scope against velocity. Triggers on: sprint planning, sprint plan, capacity planning, sprint scope, story points, sprint goal, backlog grooming, sprint prep, what do we build this sprint."
---

# Sprint Plan

## Core Philosophy

Sprint planning is a commitment, not a wish list. The goal is not to stuff the sprint with as many stories as possible — it's to make a realistic promise the team can keep. An under-committed sprint that ships is better than an over-committed sprint that leaves things half-done.

The sprint goal is the contract. Every story in the sprint should directly serve it.

## When to Use

- Before the start of a new sprint
- When backlog needs to be sequenced and stories need capacity estimates
- When a sprint is at risk and scope needs to be cut

## Workflow

### 1. Set the Sprint Goal

One sentence. What does success look like at the end of this sprint — from a user or business perspective, not an engineering perspective?

- Bad: "Complete stories 45-52"
- Good: "Users can complete onboarding without contacting support"

The sprint goal is the tiebreaker when scope decisions arise mid-sprint.

### 2. Estimate Team Capacity

- List each team member and their availability (working days minus PTO, holidays, on-call)
- Reference velocity from the last 3 sprints (average story points completed)
- Apply a 15-20% buffer for unexpected work, bugs, and interruptions
- Result: Available capacity in story points for this sprint

### 3. Select Stories from the Prioritized Backlog

- Pull from the top of the prioritized backlog (highest priority first)
- Each story must meet the Definition of Ready: clear acceptance criteria, estimated, no open blockers
- Flag stories that need refinement — don't commit to them until they're ready
- Stop adding stories when capacity is reached

### 4. Map Dependencies

- Identify which stories depend on other stories or external teams
- Sequence dependent stories appropriately (don't start Story B before Story A is done)
- Flag external dependencies by name: who owns them, what's the expected date?
- Identify the critical path — the sequence of stories that determines the minimum sprint duration

### 5. Identify Risks

- High uncertainty stories (large unknowns in implementation)
- External dependencies that could slip
- Knowledge concentration (only one person can do it)
- For each risk: suggest a mitigation or a decision point

### 6. Write the Sprint Summary

## Output Format

```
## Sprint Plan — Sprint [N] — [Start Date] to [End Date]

**Sprint Goal**: [One sentence — user or business outcome]

**Team Capacity**
- Available: [X] story points
- Committed: [Y] story points
- Buffer: [Z] story points

**Stories Committed**
| Story | Points | Owner | Dependencies |
|---|---|---|---|
| [Title] | [pts] | [name] | [none / Story X / Team Y] |

**Dependencies**
- [External dependency] — Owner: [name] — Expected: [date]

**Risks**
| Risk | Mitigation |
|---|---|
| [High uncertainty in Story X] | [Spike in Day 1-2 to reduce unknowns] |

**Critical Path**
[Story A] → [Story B] → [Story C]
```

## Antipatterns

- **Optimistic capacity**: Not accounting for meetings, reviews, on-call, or context-switching. Real capacity is typically 60-70% of theoretical hours.
- **No sprint goal**: A sprint with only a story list has no North Star for mid-sprint decisions. When something breaks, what gets cut?
- **Committing unready stories**: Starting a sprint with stories that don't have clear acceptance criteria. They'll block mid-sprint.
- **Ignoring dependencies**: Discovering that Story B can't start because Team X hasn't delivered their API — on Day 3 of the sprint.
- **Velocity as a target**: Velocity is a planning tool, not a performance metric. Pressuring teams to hit a velocity number inflates estimates over time.

Attribution

Is this your skill, or is something wrong with this listing? Request removal or report an issue. Author removals are honored within 72 hours.

Comments

Loading comments…