ASecurityProcess and manage construction change orders. Track costs, approvals, and impact on schedule and budget.
- 299 stars
- 0 votes
- 0 copies
- 2 views
- Added February 7, 2026
Security analysis
100/100npx -y skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill change-order-processor --agent claude-codeAre you the author of Change Order Processor?
Add the live security badge to your README. It updates with every re-scan.
[](https://www.skillsdirectory.com/skills/datadrivenconstruction-change-order-processor)---
slug: "change-order-processor"
display_name: "Change Order Processor"
description: "Process and manage construction change orders. Track costs, approvals, and impact on schedule and budget."
---
# Change Order Processor
## Business Case
### Problem Statement
Change orders cause project disruption:
- Delayed processing affects cash flow
- Unclear cost impact
- Lost documentation
- Schedule impacts not tracked
### Solution
Streamlined change order processing with cost analysis, approval workflow, and impact tracking.
### Business Value
- **Faster processing** - Reduce approval cycle time
- **Cost control** - Accurate change pricing
- **Documentation** - Complete audit trail
- **Impact visibility** - Schedule and budget effects
## Technical Implementation
```python
import pandas as pd
from datetime import datetime, date, timedelta
from typing import Dict, Any, List, Optional
from dataclasses import dataclass, field
from enum import Enum
class ChangeOrderStatus(Enum):
"""Change order status."""
DRAFT = "draft"
PENDING_REVIEW = "pending_review"
PENDING_APPROVAL = "pending_approval"
APPROVED = "approved"
REJECTED = "rejected"
VOID = "void"
class ChangeType(Enum):
"""Type of change."""
OWNER_REQUESTED = "owner_requested"
DESIGN_CHANGE = "design_change"
FIELD_CONDITION = "field_condition"
CODE_COMPLIANCE = "code_compliance"
VALUE_ENGINEERING = "value_engineering"
ERROR_OMISSION = "error_omission"
class ImpactType(Enum):
"""Impact categories."""
COST_INCREASE = "cost_increase"
COST_DECREASE = "cost_decrease"
TIME_INCREASE = "time_increase"
TIME_DECREASE = "time_decrease"
NO_IMPACT = "no_impact"
@dataclass
class CostItem:
"""Change order cost item."""
description: str
quantity: float
unit: str
unit_cost: float
total_cost: float
category: str # labor, material, equipment, subcontractor
markup_percent: float = 0.0
@dataclass
class ApprovalRecord:
"""Approval workflow record."""
approver_name: str
approver_role: str
action: str # approved, rejected, returned
action_date: datetime
comments: str = ""
@dataclass
class ChangeOrder:
"""Change order record."""
co_number: str
title: str
description: str
change_type: ChangeType
status: ChangeOrderStatus
created_date: date
created_by: str
# Cost
cost_items: List[CostItem] = field(default_factory=list)
direct_cost: float = 0.0
overhead_cost: float = 0.0
profit_cost: float = 0.0
total_cost: float = 0.0
# Schedule
schedule_impact_days: int = 0
affected_activities: List[str] = field(default_factory=list)
# Workflow
approvals: List[ApprovalRecord] = field(default_factory=list)
approved_date: Optional[date] = None
approved_by: str = ""
# References
rfi_reference: str = ""
spec_section: str = ""
drawing_reference: str = ""
location: str = ""
def to_dict(self) -> Dict[str, Any]:
return {
'co_number': self.co_number,
'title': self.title,
'change_type': self.change_type.value,
'status': self.status.value,
'created_date': self.created_date.isoformat(),
'direct_cost': self.direct_cost,
'overhead_cost': self.overhead_cost,
'profit_cost': self.profit_cost,
'total_cost': self.total_cost,
'schedule_impact': self.schedule_impact_days,
'approved_date': self.approved_date.isoformat() if self.approved_date else None
}
class ChangeOrderProcessor:
"""Process and manage change orders."""
DEFAULT_OVERHEAD_RATE = 0.10
DEFAULT_PROFIT_RATE = 0.10
def __init__(self, project_name: str, original_contract: float,
overhead_rate: float = None, profit_rate: float = None):
self.project_name = project_name
self.original_contract = original_contract
self.overhead_rate = overhead_rate or self.DEFAULT_OVERHEAD_RATE
self.profit_rate = profit_rate or self.DEFAULT_PROFIT_RATE
self.change_orders: Dict[str, ChangeOrder] = {}
self._co_counter = 0
def create_change_order(self,
title: str,
description: str,
change_type: ChangeType,
created_by: str,
rfi_reference: str = "",
location: str = "") -> ChangeOrder:
"""Create new change order."""
self._co_counter += 1
co_number = f"CO-{self._co_counter:04d}"
co = ChangeOrder(
co_number=co_number,
title=title,
description=description,
change_type=change_type,
status=ChangeOrderStatus.DRAFT,
created_date=date.today(),
created_by=created_by,
rfi_reference=rfi_reference,
location=location
)
self.change_orders[co_number] = co
return co
def add_cost_item(self, co_number: str,
description: str,
quantity: float,
unit: str,
unit_cost: float,
category: str,
markup_percent: float = 0.0):
"""Add cost item to change order."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
total = quantity * unit_cost * (1 + markup_percent)
item = CostItem(
description=description,
quantity=quantity,
unit=unit,
unit_cost=unit_cost,
total_cost=total,
category=category,
markup_percent=markup_percent
)
co.cost_items.append(item)
self._recalculate_totals(co)
def _recalculate_totals(self, co: ChangeOrder):
"""Recalculate change order totals."""
co.direct_cost = sum(item.total_cost for item in co.cost_items)
co.overhead_cost = co.direct_cost * self.overhead_rate
co.profit_cost = (co.direct_cost + co.overhead_cost) * self.profit_rate
co.total_cost = co.direct_cost + co.overhead_cost + co.profit_cost
def set_schedule_impact(self, co_number: str, days: int,
affected_activities: List[str] = None):
"""Set schedule impact."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
co.schedule_impact_days = days
co.affected_activities = affected_activities or []
def submit_for_review(self, co_number: str):
"""Submit change order for review."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
if co.status != ChangeOrderStatus.DRAFT:
raise ValueError("Can only submit draft change orders")
co.status = ChangeOrderStatus.PENDING_REVIEW
def submit_for_approval(self, co_number: str, reviewer: str, comments: str = ""):
"""Submit for approval after review."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
if co.status != ChangeOrderStatus.PENDING_REVIEW:
raise ValueError("Must be in review status")
co.approvals.append(ApprovalRecord(
approver_name=reviewer,
approver_role="Reviewer",
action="reviewed",
action_date=datetime.now(),
comments=comments
))
co.status = ChangeOrderStatus.PENDING_APPROVAL
def approve_change_order(self, co_number: str, approver: str,
approver_role: str, comments: str = ""):
"""Approve change order."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
co.approvals.append(ApprovalRecord(
approver_name=approver,
approver_role=approver_role,
action="approved",
action_date=datetime.now(),
comments=comments
))
co.status = ChangeOrderStatus.APPROVED
co.approved_date = date.today()
co.approved_by = approver
def reject_change_order(self, co_number: str, rejector: str,
reason: str):
"""Reject change order."""
if co_number not in self.change_orders:
raise ValueError(f"Change order {co_number} not found")
co = self.change_orders[co_number]
co.approvals.append(ApprovalRecord(
approver_name=rejector,
approver_role="Approver",
action="rejected",
action_date=datetime.now(),
comments=reason
))
co.status = ChangeOrderStatus.REJECTED
def get_summary(self) -> Dict[str, Any]:
"""Generate change order summary."""
cos = list(self.change_orders.values())
by_status = {}
by_type = {}
total_approved = 0
total_pending = 0
total_schedule_impact = 0
for co in cos:
# By status
status = co.status.value
by_status[status] = by_status.get(status, 0) + 1
# By type
change_type = co.change_type.value
by_type[change_type] = by_type.get(change_type, 0) + co.total_cost
# Totals
if co.status == ChangeOrderStatus.APPROVED:
total_approved += co.total_cost
total_schedule_impact += co.schedule_impact_days
elif co.status in [ChangeOrderStatus.PENDING_REVIEW, ChangeOrderStatus.PENDING_APPROVAL]:
total_pending += co.total_cost
current_contract = self.original_contract + total_approved
return {
'project': self.project_name,
'original_contract': self.original_contract,
'approved_changes': total_approved,
'current_contract': current_contract,
'pending_changes': total_pending,
'potential_contract': current_contract + total_pending,
'total_change_orders': len(cos),
'by_status': by_status,
'by_type': by_type,
'total_schedule_impact_days': total_schedule_impact,
'change_percent': round(total_approved / self.original_contract * 100, 1) if self.original_contract > 0 else 0
}
def get_pending_approvals(self) -> List[ChangeOrder]:
"""Get change orders pending approval."""
return [co for co in self.change_orders.values()
if co.status in [ChangeOrderStatus.PENDING_REVIEW, ChangeOrderStatus.PENDING_APPROVAL]]
def export_log(self, output_path: str):
"""Export change order log to Excel."""
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Summary
summary = self.get_summary()
summary_df = pd.DataFrame([
{'Metric': 'Original Contract', 'Value': summary['original_contract']},
{'Metric': 'Approved Changes', 'Value': summary['approved_changes']},
{'Metric': 'Current Contract', 'Value': summary['current_contract']},
{'Metric': 'Pending Changes', 'Value': summary['pending_changes']},
{'Metric': 'Change %', 'Value': f"{summary['change_percent']}%"},
{'Metric': 'Schedule Impact (days)', 'Value': summary['total_schedule_impact_days']}
])
summary_df.to_excel(writer, sheet_name='Summary', index=False)
# Change order list
co_data = [co.to_dict() for co in self.change_orders.values()]
pd.DataFrame(co_data).to_excel(writer, sheet_name='Change Orders', index=False)
# Cost details
cost_data = []
for co in self.change_orders.values():
for item in co.cost_items:
cost_data.append({
'CO Number': co.co_number,
'Description': item.description,
'Quantity': item.quantity,
'Unit': item.unit,
'Unit Cost': item.unit_cost,
'Total': item.total_cost,
'Category': item.category
})
if cost_data:
pd.DataFrame(cost_data).to_excel(writer, sheet_name='Cost Details', index=False)
return output_path
```
## Quick Start
```python
# Initialize processor
processor = ChangeOrderProcessor(
project_name="Office Tower",
original_contract=50000000
)
# Create change order
co = processor.create_change_order(
title="Additional Electrical Outlets",
description="Add 50 electrical outlets per owner request",
change_type=ChangeType.OWNER_REQUESTED,
created_by="Project Manager"
)
# Add cost items
processor.add_cost_item(co.co_number, "Electrical outlets", 50, "EA", 150, "material")
processor.add_cost_item(co.co_number, "Installation labor", 25, "HR", 85, "labor")
# Set schedule impact
processor.set_schedule_impact(co.co_number, days=5)
# Submit for approval
processor.submit_for_review(co.co_number)
```
## Common Use Cases
### 1. Process Approval
```python
processor.submit_for_approval(co.co_number, "Reviewer", "Cost verified")
processor.approve_change_order(co.co_number, "Owner Rep", "Owner", "Approved per request")
```
### 2. Get Summary
```python
summary = processor.get_summary()
print(f"Contract value: ${summary['current_contract']:,.0f}")
print(f"Change %: {summary['change_percent']}%")
```
### 3. Export Log
```python
processor.export_log("change_order_log.xlsx")
```
## Resources
- **DDC Book**: Chapter 3.1 - Cost Management
- **Reference**: AIA Document G701