Delay Analysis
ASecurityAnalyze construction schedule delays for claims and recovery. Perform time impact analysis, identify delay causes, calculate damages, and document for disputes.
- 299 stars
- 0 votes
- 0 copies
- 1 view
- Added February 7, 2026
Security analysis
96/100- Installs packages at runtime which could introduce malicious dependencies
npx -y skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill delay-analysis --agent claude-codeAre you the author of Delay Analysis?
Add the live security badge to your README. It updates with every re-scan.
[](https://www.skillsdirectory.com/skills/datadrivenconstruction-delay-analysis)---
slug: "delay-analysis"
display_name: "Delay Analysis"
description: "Analyze construction schedule delays for claims and recovery. Perform time impact analysis, identify delay causes, calculate damages, and document for disputes."
---
# Delay Analysis
## Overview
Analyze construction schedule delays for project recovery and claims. Perform time impact analysis (TIA), identify concurrent delays, calculate delay damages, and prepare documentation for dispute resolution.
> "Proper delay analysis is essential for fair resolution of construction disputes" — DDC Community
## Delay Analysis Methods
```
┌─────────────────────────────────────────────────────────────────┐
│ DELAY ANALYSIS METHODS │
├─────────────────────────────────────────────────────────────────┤
│ │
│ As-Planned vs As-Built │ Time Impact Analysis (TIA) │
│ ───────────────────── │ ──────────────────────────── │
│ Compare original to │ Insert delay events into │
│ actual schedule │ schedule to measure impact │
│ │ │
│ Windows Analysis │ Collapsed As-Built │
│ ──────────────── │ ───────────────── │
│ Divide project into │ Remove delays from as-built │
│ time periods │ to find "but-for" completion │
│ │
└─────────────────────────────────────────────────────────────────┘
```
## Technical Implementation
```python
from dataclasses import dataclass, field
from typing import List, Dict, Optional, Tuple
from datetime import datetime, timedelta
from enum import Enum
from collections import defaultdict
class DelayType(Enum):
EXCUSABLE_COMPENSABLE = "excusable_compensable" # Owner caused - time + money
EXCUSABLE_NON_COMPENSABLE = "excusable_non_compensable" # Neither party - time only
NON_EXCUSABLE = "non_excusable" # Contractor caused - no relief
CONCURRENT = "concurrent" # Both parties - complex
class DelayCause(Enum):
OWNER_CHANGE = "owner_change"
LATE_INFORMATION = "late_information"
DIFFERING_CONDITIONS = "differing_conditions"
PERMIT_DELAY = "permit_delay"
WEATHER = "weather"
LABOR_SHORTAGE = "labor_shortage"
MATERIAL_DELAY = "material_delay"
SUBCONTRACTOR = "subcontractor"
COORDINATION = "coordination"
ACCESS = "access"
FORCE_MAJEURE = "force_majeure"
@dataclass
class DelayEvent:
id: str
description: str
cause: DelayCause
delay_type: DelayType
start_date: datetime
end_date: datetime
affected_activities: List[str]
responsible_party: str
documented: bool = True
supporting_docs: List[str] = field(default_factory=list)
calculated_impact: int = 0 # days
concurrent_with: List[str] = field(default_factory=list)
@dataclass
class ScheduleVersion:
version_id: str
version_type: str # baseline, update, as-built
data_date: datetime
completion_date: datetime
activities: Dict[str, Dict] # activity_id -> {start, finish, duration}
@dataclass
class WindowPeriod:
window_id: str
start_date: datetime
end_date: datetime
planned_progress: float
actual_progress: float
delay_days: int
delay_events: List[str]
responsible_parties: Dict[str, int] # party -> delay days
@dataclass
class DelayAnalysisReport:
project_name: str
analysis_date: datetime
original_completion: datetime
actual_completion: datetime
total_delay: int
excusable_delay: int
non_excusable_delay: int
concurrent_delay: int
delay_events: List[DelayEvent]
delay_by_cause: Dict[str, int]
delay_by_party: Dict[str, int]
recommended_extension: int
potential_damages: float
class DelayAnalyzer:
"""Analyze construction schedule delays."""
# Daily delay costs by project size
DEFAULT_DAILY_COSTS = {
"small": 5000, # < $10M
"medium": 15000, # $10M - $50M
"large": 40000, # $50M - $200M
"mega": 100000 # > $200M
}
def __init__(self, project_name: str, contract_completion: datetime):
self.project_name = project_name
self.contract_completion = contract_completion
self.delay_events: Dict[str, DelayEvent] = {}
self.schedule_versions: Dict[str, ScheduleVersion] = {}
self.window_periods: List[WindowPeriod] = []
self.daily_cost = self.DEFAULT_DAILY_COSTS["medium"]
def set_daily_delay_cost(self, cost: float):
"""Set daily delay cost for damages calculation."""
self.daily_cost = cost
def add_schedule_version(self, version_id: str, version_type: str,
data_date: datetime, completion_date: datetime,
activities: Dict[str, Dict]) -> ScheduleVersion:
"""Add schedule version for analysis."""
version = ScheduleVersion(
version_id=version_id,
version_type=version_type,
data_date=data_date,
completion_date=completion_date,
activities=activities
)
self.schedule_versions[version_id] = version
return version
def add_delay_event(self, id: str, description: str,
cause: DelayCause, delay_type: DelayType,
start_date: datetime, end_date: datetime,
affected_activities: List[str],
responsible_party: str,
supporting_docs: List[str] = None) -> DelayEvent:
"""Add delay event for analysis."""
event = DelayEvent(
id=id,
description=description,
cause=cause,
delay_type=delay_type,
start_date=start_date,
end_date=end_date,
affected_activities=affected_activities,
responsible_party=responsible_party,
supporting_docs=supporting_docs or []
)
self.delay_events[id] = event
return event
def perform_as_planned_vs_as_built(self) -> Dict:
"""Perform As-Planned vs As-Built analysis."""
baseline = self.schedule_versions.get("baseline")
as_built = self.schedule_versions.get("as_built")
if not baseline or not as_built:
raise ValueError("Need baseline and as-built schedules")
total_delay = (as_built.completion_date - baseline.completion_date).days
# Analyze each activity
activity_delays = []
for act_id, baseline_act in baseline.activities.items():
if act_id in as_built.activities:
as_built_act = as_built.activities[act_id]
baseline_finish = baseline_act['finish']
actual_finish = as_built_act['finish']
if isinstance(baseline_finish, str):
baseline_finish = datetime.fromisoformat(baseline_finish)
if isinstance(actual_finish, str):
actual_finish = datetime.fromisoformat(actual_finish)
delay = (actual_finish - baseline_finish).days
if delay > 0:
activity_delays.append({
'activity_id': act_id,
'planned_finish': baseline_finish,
'actual_finish': actual_finish,
'delay_days': delay
})
return {
'method': 'As-Planned vs As-Built',
'baseline_completion': baseline.completion_date,
'actual_completion': as_built.completion_date,
'total_delay': total_delay,
'activity_delays': sorted(activity_delays, key=lambda x: -x['delay_days'])
}
def perform_time_impact_analysis(self, delay_event_id: str) -> Dict:
"""Perform Time Impact Analysis for specific delay event."""
if delay_event_id not in self.delay_events:
raise ValueError(f"Delay event {delay_event_id} not found")
event = self.delay_events[delay_event_id]
# Find schedule version just before delay
pre_delay_schedule = None
for version in sorted(self.schedule_versions.values(),
key=lambda v: v.data_date, reverse=True):
if version.data_date < event.start_date:
pre_delay_schedule = version
break
if not pre_delay_schedule:
pre_delay_schedule = self.schedule_versions.get("baseline")
if not pre_delay_schedule:
raise ValueError("No pre-delay schedule found")
# Calculate impact
original_completion = pre_delay_schedule.completion_date
delay_duration = (event.end_date - event.start_date).days
# Check if delay is on critical path
critical_impact = False
for act_id in event.affected_activities:
if act_id in pre_delay_schedule.activities:
act = pre_delay_schedule.activities[act_id]
if act.get('is_critical', False):
critical_impact = True
break
if critical_impact:
impact_days = delay_duration
new_completion = original_completion + timedelta(days=delay_duration)
else:
# Need to check float
impact_days = max(0, delay_duration - 5) # Simplified - assume 5 days float
new_completion = original_completion + timedelta(days=impact_days)
event.calculated_impact = impact_days
return {
'method': 'Time Impact Analysis',
'delay_event': event.id,
'delay_description': event.description,
'delay_duration': delay_duration,
'critical_path_impact': critical_impact,
'schedule_impact_days': impact_days,
'original_completion': original_completion,
'impacted_completion': new_completion,
'delay_type': event.delay_type.value,
'responsible_party': event.responsible_party
}
def identify_concurrent_delays(self) -> List[Tuple[str, str, int]]:
"""Identify concurrent delay events."""
concurrent = []
events = list(self.delay_events.values())
for i, event1 in enumerate(events):
for event2 in events[i+1:]:
# Check for overlap
overlap_start = max(event1.start_date, event2.start_date)
overlap_end = min(event1.end_date, event2.end_date)
if overlap_start < overlap_end:
overlap_days = (overlap_end - overlap_start).days
concurrent.append((event1.id, event2.id, overlap_days))
event1.concurrent_with.append(event2.id)
event2.concurrent_with.append(event1.id)
return concurrent
def perform_windows_analysis(self, window_days: int = 30) -> List[WindowPeriod]:
"""Perform windows analysis by dividing project into periods."""
baseline = self.schedule_versions.get("baseline")
as_built = self.schedule_versions.get("as_built")
if not baseline or not as_built:
raise ValueError("Need baseline and as-built schedules")
windows = []
current_start = baseline.data_date
window_num = 1
while current_start < as_built.completion_date:
window_end = min(
current_start + timedelta(days=window_days),
as_built.completion_date
)
# Find delay events in this window
window_events = [
e.id for e in self.delay_events.values()
if e.start_date < window_end and e.end_date > current_start
]
# Calculate delay by party
party_delays = defaultdict(int)
for event_id in window_events:
event = self.delay_events[event_id]
overlap_start = max(event.start_date, current_start)
overlap_end = min(event.end_date, window_end)
days = (overlap_end - overlap_start).days
party_delays[event.responsible_party] += days
window = WindowPeriod(
window_id=f"W{window_num:02d}",
start_date=current_start,
end_date=window_end,
planned_progress=0.0, # Would calculate from schedule
actual_progress=0.0,
delay_days=sum(party_delays.values()),
delay_events=window_events,
responsible_parties=dict(party_delays)
)
windows.append(window)
current_start = window_end
window_num += 1
self.window_periods = windows
return windows
def calculate_delay_damages(self) -> Dict:
"""Calculate potential delay damages."""
# Summarize delays by type
excusable_compensable = 0
excusable_non_compensable = 0
non_excusable = 0
for event in self.delay_events.values():
impact = event.calculated_impact or (event.end_date - event.start_date).days
# Adjust for concurrency
if event.concurrent_with:
impact = impact // 2 # Simplified concurrency handling
if event.delay_type == DelayType.EXCUSABLE_COMPENSABLE:
excusable_compensable += impact
elif event.delay_type == DelayType.EXCUSABLE_NON_COMPENSABLE:
excusable_non_compensable += impact
elif event.delay_type == DelayType.NON_EXCUSABLE:
non_excusable += impact
# Calculate damages
contractor_damages = excusable_compensable * self.daily_cost
owner_ld = non_excusable * self.daily_cost
return {
'excusable_compensable_days': excusable_compensable,
'excusable_non_compensable_days': excusable_non_compensable,
'non_excusable_days': non_excusable,
'recommended_time_extension': excusable_compensable + excusable_non_compensable,
'contractor_delay_damages': contractor_damages,
'owner_liquidated_damages': owner_ld,
'daily_rate_used': self.daily_cost
}
def generate_analysis_report(self, actual_completion: datetime) -> DelayAnalysisReport:
"""Generate comprehensive delay analysis report."""
total_delay = (actual_completion - self.contract_completion).days
# Categorize delays
delay_by_cause = defaultdict(int)
delay_by_party = defaultdict(int)
excusable = 0
non_excusable = 0
concurrent = 0
for event in self.delay_events.values():
impact = event.calculated_impact or (event.end_date - event.start_date).days
delay_by_cause[event.cause.value] += impact
delay_by_party[event.responsible_party] += impact
if event.concurrent_with:
concurrent += impact // 2
elif event.delay_type in [DelayType.EXCUSABLE_COMPENSABLE,
DelayType.EXCUSABLE_NON_COMPENSABLE]:
excusable += impact
else:
non_excusable += impact
damages = self.calculate_delay_damages()
return DelayAnalysisReport(
project_name=self.project_name,
analysis_date=datetime.now(),
original_completion=self.contract_completion,
actual_completion=actual_completion,
total_delay=total_delay,
excusable_delay=excusable,
non_excusable_delay=non_excusable,
concurrent_delay=concurrent,
delay_events=list(self.delay_events.values()),
delay_by_cause=dict(delay_by_cause),
delay_by_party=dict(delay_by_party),
recommended_extension=damages['recommended_time_extension'],
potential_damages=damages['contractor_delay_damages']
)
def generate_report_markdown(self, report: DelayAnalysisReport) -> str:
"""Generate markdown report."""
lines = [
"# Delay Analysis Report",
"",
f"**Project:** {report.project_name}",
f"**Analysis Date:** {report.analysis_date.strftime('%Y-%m-%d')}",
"",
"## Schedule Summary",
"",
f"| Milestone | Date |",
f"|-----------|------|",
f"| Contract Completion | {report.original_completion.strftime('%Y-%m-%d')} |",
f"| Actual Completion | {report.actual_completion.strftime('%Y-%m-%d')} |",
f"| **Total Delay** | **{report.total_delay} days** |",
"",
"## Delay Classification",
"",
f"| Category | Days |",
f"|----------|------|",
f"| Excusable Delay | {report.excusable_delay} |",
f"| Non-Excusable Delay | {report.non_excusable_delay} |",
f"| Concurrent Delay | {report.concurrent_delay} |",
"",
"## Delay by Cause",
""
]
for cause, days in sorted(report.delay_by_cause.items(), key=lambda x: -x[1]):
lines.append(f"- **{cause}**: {days} days")
lines.extend([
"",
"## Delay by Responsible Party",
""
])
for party, days in sorted(report.delay_by_party.items(), key=lambda x: -x[1]):
lines.append(f"- **{party}**: {days} days")
lines.extend([
"",
"## Recommendations",
"",
f"- **Recommended Time Extension:** {report.recommended_extension} days",
f"- **Potential Delay Damages:** ${report.potential_damages:,.0f}",
""
])
return "\n".join(lines)
```
## Quick Start
```python
from datetime import datetime, timedelta
# Initialize analyzer
analyzer = DelayAnalyzer(
"Office Tower",
contract_completion=datetime(2024, 12, 31)
)
# Add schedule versions
analyzer.add_schedule_version(
"baseline", "baseline",
datetime(2024, 1, 1),
datetime(2024, 12, 31),
activities={"A100": {"finish": datetime(2024, 6, 30), "is_critical": True}}
)
analyzer.add_schedule_version(
"as_built", "as_built",
datetime(2025, 3, 15),
datetime(2025, 3, 15),
activities={"A100": {"finish": datetime(2024, 8, 15)}}
)
# Add delay events
analyzer.add_delay_event(
"D001",
"Owner-directed design change to HVAC system",
DelayCause.OWNER_CHANGE,
DelayType.EXCUSABLE_COMPENSABLE,
datetime(2024, 4, 1),
datetime(2024, 5, 15),
["A100", "A101"],
"Owner"
)
analyzer.add_delay_event(
"D002",
"Unexpected rock encountered in excavation",
DelayCause.DIFFERING_CONDITIONS,
DelayType.EXCUSABLE_COMPENSABLE,
datetime(2024, 3, 15),
datetime(2024, 4, 30),
["A050"],
"Owner"
)
# Perform analyses
tia = analyzer.perform_time_impact_analysis("D001")
print(f"TIA Impact: {tia['schedule_impact_days']} days")
concurrent = analyzer.identify_concurrent_delays()
print(f"Concurrent delays found: {len(concurrent)}")
# Generate report
report = analyzer.generate_analysis_report(datetime(2025, 3, 15))
print(analyzer.generate_report_markdown(report))
```