Back to skills
SKILL.md
Schedule Cost Link
ASecurityLink schedule activities to cost items. Create cost-loaded schedules, generate cash flow curves, and track earned value.
- 299 stars
- 0 votes
- 0 copies
- 0 views
- Added February 7, 2026
Security analysis
100/100npx -y skills add datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction --skill schedule-cost-link --agent claude-codeAre you the author of Schedule Cost Link?
Add the live security badge to your README. It updates with every re-scan.
[](https://www.skillsdirectory.com/skills/datadrivenconstruction-schedule-cost-link)---
slug: "schedule-cost-link"
display_name: "Schedule Cost Link"
description: "Link schedule activities to cost items. Create cost-loaded schedules, generate cash flow curves, and track earned value."
---
# Schedule-Cost Linker
## Business Case
### Problem Statement
Integrating schedule and cost requires:
- Linking activities to budget items
- Creating cost-loaded schedules
- Generating cash flow forecasts
- Tracking earned value metrics
### Solution
Systematic linkage between schedule activities and cost data to enable integrated project control.
## Technical Implementation
```python
import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Tuple
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict
class LoadingMethod(Enum):
UNIFORM = "uniform" # Even distribution
FRONT_LOADED = "front_loaded"
BACK_LOADED = "back_loaded"
BELL_CURVE = "bell_curve"
@dataclass
class ScheduleActivity:
activity_id: str
name: str
start_date: date
finish_date: date
duration: int
percent_complete: float = 0
@dataclass
class CostItem:
cost_code: str
description: str
budgeted_cost: float
labor_cost: float
material_cost: float
equipment_cost: float
@dataclass
class ActivityCostLink:
activity_id: str
cost_code: str
budgeted_cost: float
loading_method: LoadingMethod
@dataclass
class EarnedValueMetrics:
data_date: date
bcws: float # Budgeted Cost of Work Scheduled (PV)
bcwp: float # Budgeted Cost of Work Performed (EV)
acwp: float # Actual Cost of Work Performed (AC)
sv: float # Schedule Variance
cv: float # Cost Variance
spi: float # Schedule Performance Index
cpi: float # Cost Performance Index
eac: float # Estimate at Completion
etc: float # Estimate to Complete
vac: float # Variance at Completion
class ScheduleCostLinker:
"""Link schedule activities to cost items."""
def __init__(self, project_name: str, budget_at_completion: float):
self.project_name = project_name
self.bac = budget_at_completion
self.activities: Dict[str, ScheduleActivity] = {}
self.cost_items: Dict[str, CostItem] = {}
self.links: List[ActivityCostLink] = []
self.actual_costs: Dict[str, float] = {} # activity_id -> actual cost
def add_activity(self,
activity_id: str,
name: str,
start_date: date,
finish_date: date,
percent_complete: float = 0):
"""Add schedule activity."""
duration = (finish_date - start_date).days + 1
self.activities[activity_id] = ScheduleActivity(
activity_id=activity_id,
name=name,
start_date=start_date,
finish_date=finish_date,
duration=duration,
percent_complete=percent_complete
)
def add_cost_item(self,
cost_code: str,
description: str,
budgeted_cost: float,
labor_pct: float = 0.4,
material_pct: float = 0.5,
equipment_pct: float = 0.1):
"""Add cost item."""
self.cost_items[cost_code] = CostItem(
cost_code=cost_code,
description=description,
budgeted_cost=budgeted_cost,
labor_cost=budgeted_cost * labor_pct,
material_cost=budgeted_cost * material_pct,
equipment_cost=budgeted_cost * equipment_pct
)
def link_activity_cost(self,
activity_id: str,
cost_code: str,
loading_method: LoadingMethod = LoadingMethod.UNIFORM):
"""Link activity to cost item."""
if activity_id not in self.activities:
return
cost_item = self.cost_items.get(cost_code)
budgeted = cost_item.budgeted_cost if cost_item else 0
self.links.append(ActivityCostLink(
activity_id=activity_id,
cost_code=cost_code,
budgeted_cost=budgeted,
loading_method=loading_method
))
def record_actual_cost(self, activity_id: str, actual_cost: float):
"""Record actual cost for activity."""
self.actual_costs[activity_id] = actual_cost
def _distribute_cost(self,
cost: float,
start_date: date,
duration: int,
method: LoadingMethod) -> Dict[date, float]:
"""Distribute cost over activity duration."""
daily_costs = {}
if duration <= 0:
return {start_date: cost}
if method == LoadingMethod.UNIFORM:
daily = cost / duration
for i in range(duration):
daily_costs[start_date + timedelta(days=i)] = daily
elif method == LoadingMethod.FRONT_LOADED:
total_weight = sum(range(duration, 0, -1))
for i in range(duration):
weight = (duration - i) / total_weight
daily_costs[start_date + timedelta(days=i)] = cost * weight
elif method == LoadingMethod.BACK_LOADED:
total_weight = sum(range(1, duration + 1))
for i in range(duration):
weight = (i + 1) / total_weight
daily_costs[start_date + timedelta(days=i)] = cost * weight
elif method == LoadingMethod.BELL_CURVE:
# Simplified bell curve
mid = duration / 2
for i in range(duration):
distance = abs(i - mid)
weight = 1 - (distance / mid) * 0.5
daily_costs[start_date + timedelta(days=i)] = cost * weight / duration
return daily_costs
def generate_cost_loaded_schedule(self) -> pd.DataFrame:
"""Generate cost-loaded schedule."""
data = []
for link in self.links:
activity = self.activities.get(link.activity_id)
cost_item = self.cost_items.get(link.cost_code)
if activity and cost_item:
data.append({
'Activity ID': activity.activity_id,
'Activity Name': activity.name,
'Cost Code': link.cost_code,
'Description': cost_item.description,
'Start': activity.start_date,
'Finish': activity.finish_date,
'Duration': activity.duration,
'Budget': link.budgeted_cost,
'% Complete': activity.percent_complete,
'Earned Value': link.budgeted_cost * activity.percent_complete / 100,
'Loading': link.loading_method.value
})
return pd.DataFrame(data)
def generate_cash_flow(self,
project_start: date = None,
project_end: date = None) -> pd.DataFrame:
"""Generate cash flow curve."""
if not self.links:
return pd.DataFrame()
# Get date range
if project_start is None:
project_start = min(self.activities[l.activity_id].start_date for l in self.links)
if project_end is None:
project_end = max(self.activities[l.activity_id].finish_date for l in self.links)
# Aggregate daily costs
daily_totals = defaultdict(float)
for link in self.links:
activity = self.activities.get(link.activity_id)
if not activity:
continue
daily_costs = self._distribute_cost(
link.budgeted_cost,
activity.start_date,
activity.duration,
link.loading_method
)
for day, cost in daily_costs.items():
daily_totals[day] += cost
# Build cash flow data
data = []
cumulative = 0
current = project_start
while current <= project_end:
daily = daily_totals.get(current, 0)
cumulative += daily
data.append({
'Date': current,
'Daily': round(daily, 2),
'Cumulative': round(cumulative, 2),
'Cumulative %': round(cumulative / self.bac * 100, 1) if self.bac > 0 else 0
})
current += timedelta(days=1)
return pd.DataFrame(data)
def calculate_earned_value(self, data_date: date) -> EarnedValueMetrics:
"""Calculate earned value metrics at data date."""
# BCWS - Planned Value through data date
bcws = 0
for link in self.links:
activity = self.activities.get(link.activity_id)
if not activity:
continue
daily_costs = self._distribute_cost(
link.budgeted_cost,
activity.start_date,
activity.duration,
link.loading_method
)
for day, cost in daily_costs.items():
if day <= data_date:
bcws += cost
# BCWP - Earned Value (budget * % complete)
bcwp = 0
for link in self.links:
activity = self.activities.get(link.activity_id)
if activity:
bcwp += link.budgeted_cost * activity.percent_complete / 100
# ACWP - Actual Cost
acwp = sum(self.actual_costs.values())
# Variances
sv = bcwp - bcws
cv = bcwp - acwp
# Indices
spi = bcwp / bcws if bcws > 0 else 0
cpi = bcwp / acwp if acwp > 0 else 0
# Forecasts
eac = self.bac / cpi if cpi > 0 else self.bac
etc = eac - acwp
vac = self.bac - eac
return EarnedValueMetrics(
data_date=data_date,
bcws=round(bcws, 2),
bcwp=round(bcwp, 2),
acwp=round(acwp, 2),
sv=round(sv, 2),
cv=round(cv, 2),
spi=round(spi, 2),
cpi=round(cpi, 2),
eac=round(eac, 2),
etc=round(etc, 2),
vac=round(vac, 2)
)
def get_monthly_cash_flow(self) -> pd.DataFrame:
"""Aggregate cash flow by month."""
daily = self.generate_cash_flow()
if daily.empty:
return pd.DataFrame()
daily['Month'] = pd.to_datetime(daily['Date']).dt.to_period('M')
monthly = daily.groupby('Month').agg({
'Daily': 'sum',
'Cumulative': 'last'
}).reset_index()
monthly.columns = ['Month', 'Monthly Cost', 'Cumulative']
return monthly
def export_to_excel(self, output_path: str) -> str:
"""Export integrated data to Excel."""
with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
# Cost-loaded schedule
schedule = self.generate_cost_loaded_schedule()
schedule.to_excel(writer, sheet_name='Cost-Loaded Schedule', index=False)
# Cash flow
cash_flow = self.generate_cash_flow()
if not cash_flow.empty:
cash_flow.to_excel(writer, sheet_name='Cash Flow', index=False)
# Monthly
monthly = self.get_monthly_cash_flow()
if not monthly.empty:
monthly.to_excel(writer, sheet_name='Monthly', index=False)
# Earned Value
evm = self.calculate_earned_value(date.today())
evm_df = pd.DataFrame([{
'Data Date': evm.data_date,
'BCWS (PV)': evm.bcws,
'BCWP (EV)': evm.bcwp,
'ACWP (AC)': evm.acwp,
'SV': evm.sv,
'CV': evm.cv,
'SPI': evm.spi,
'CPI': evm.cpi,
'EAC': evm.eac,
'ETC': evm.etc,
'VAC': evm.vac
}])
evm_df.to_excel(writer, sheet_name='Earned Value', index=False)
return output_path
```
## Quick Start
```python
from datetime import date, timedelta
# Initialize linker
linker = ScheduleCostLinker("Office Building", budget_at_completion=5000000)
# Add activities
linker.add_activity("A-001", "Foundation", date(2024, 6, 1), date(2024, 6, 30), percent_complete=100)
linker.add_activity("A-002", "Structure", date(2024, 7, 1), date(2024, 9, 30), percent_complete=60)
linker.add_activity("A-003", "MEP", date(2024, 8, 1), date(2024, 11, 30), percent_complete=30)
# Add cost items
linker.add_cost_item("01-FOUND", "Foundation Work", 500000)
linker.add_cost_item("02-STRUCT", "Structural Work", 2000000)
linker.add_cost_item("03-MEP", "MEP Systems", 1500000)
# Link
linker.link_activity_cost("A-001", "01-FOUND")
linker.link_activity_cost("A-002", "02-STRUCT", LoadingMethod.BELL_CURVE)
linker.link_activity_cost("A-003", "03-MEP", LoadingMethod.BACK_LOADED)
# Record actuals
linker.record_actual_cost("A-001", 520000)
linker.record_actual_cost("A-002", 1300000)
```
## Common Use Cases
### 1. Earned Value Analysis
```python
evm = linker.calculate_earned_value(date.today())
print(f"CPI: {evm.cpi}")
print(f"SPI: {evm.spi}")
print(f"EAC: ${evm.eac:,.2f}")
```
### 2. Cash Flow Forecast
```python
cash_flow = linker.generate_cash_flow()
print(cash_flow.tail(10))
```
### 3. Monthly Breakdown
```python
monthly = linker.get_monthly_cash_flow()
print(monthly)
```
## Resources
- **DDC Book**: Chapter 4.2 - Schedule-Cost Integration
Attribution
Comments
Loading comments…